11111
FAQ
ApplicationCase Home>>ApplicationCase>>Installation Process for Slope Construction
  

1. Preparing materials, machines and tools

Getting ready the requiired machines and tools for construction, like shovels, generators, steel drivers and so on. If the soil on the spot is rocky, the organically mixed soil need to be transported from other place for filling into the geotextile bag. 

Figure 1: the soil for filling in

2.How to install the stocking-shaped geotextile bag

Firstly,ship the filling soil by shovel onto the top of the hill. Hang down the bag from the top of the hill vertically and put the soil into the bag by conveyor belt. Than push a steel every 100cm on the bag until the bag is fully filled. Shown in figure 2-4.

 
 

Figure 2: Filling the soil into the bag from top of hill

 

 

 

 

Figure 3: Pushing the steel onto the bag

Figure 4: Construction completed

 


 

 3. Slope repaiingr and digging

After the stoking-shaped bag is installed, go on to install the geotextiles bag. Firstly, the slope must be repaired and foundation be digged to the depth in which one bag can be holded.( see figure 5 , 6)

Figure 5: repairing the slope

 
   

Figure 6: Digging

 

 


4.To install geotextile bag onto the foundation

The bag which is installed to the doundation is filled with gravel soil and sealed by the binding band so that to have drainage effect. Then stack the bag in order in a vertical direction(lenthways) and push the steel onto the bag to reinforce them. (As shown in figure 7, 8,and 9).


 

    

 Figure 7: Gravel soil to fill into the bag

 
   

Figure 8: How the bag is installed

 

 

  

Figure 9: steel pushing in front and back of the bag

 

 

5. Stack layer by layer

When the base layer is complete, put Jianchibao project fasterner on the top, and stack the geotextile bag which is filled with organically mixed soil (as shown in pic 10). Compact the bag when each layer is finished stacking. To strenthen the connection between the bag and slope, place a bag vertically to the slope on each two levelly placed bags, ,meanwhil,dig intothe slope to hold the bag and push the steel onto it to enhance its stability.(As shown in figure 12,13)

    

 Figure 10 : Stack layer by layer

Figure 11: Compacting on each layer

 

    

(a) digging into the slope

  (b) leave a hole to hold the bag vertically

 

 

Figure 12: the process of placing the geotextile bag longitudinalyy(1)  

    

(a) Pushing steels onto the inner layer

(b) the layer with steels pushed

 

 

Figure 13: the process of installing the geotextile bag longitudinalyy(2)

6.Installation on the top of the hill

The bags are stacked layer by layer until it reach the top of the hill, then goes the ending process. Firstly, place the waterproofing membrane, on which stack the bag vertically ( as shown in figure 14). Then the steels are pushed onto it to enhance connection force between the two. The waterproofing membrane plays a role of preventing water entering into the bags and slopes so as to prevent slope sliding, thus insuring the security of the structure.

 
 

Figure 14: the waterproofing membrane and the view of the bag on the top


Figure 15: a view of the slope after installation

 

7.Spraying the seeds of grass

Mix seeds of grass with organic fertilizer then spray them onto the slope directly( as shown in frgure 16).


 

 

 
Figure 16: spraying seeds of grass
 

 

Figure 17: a view after spraying seeds of grass

 

 

 

Copyright ©2010 JIANCHIBAO(FUZHOU)BUILDING MATERIALS CO., LTD. All Rights Reserved.   闽ICP备09044038号   技术支持:兴企设计  流量统计